Starting July 22 with an anticipated completion of Oct. 17, the Port of San Diego will begin revamping the parking lot at the Chula Vista Bayfront Park. This maintenance project will be done in stages to ensure pedestrian and vehicle access in both travel directions with traffic control to minimize impacts during construction.
Over the 90-day project, the park and boat launch will always be open, a section of Marina Way will be affected, no detours are required, but traffic measures will be in place, and parking will be limited with an adjacent dirt lot available for parking.
The project phases should be completed in time but are subject to changes based on construction conditions. Phase 1 is slated to be completed late July to mid-August. Phase 2, mid-August to early September, Phase 3, early September to mid-September, and Phase 4 mid-September to early October.
This project is part of the Port’s yearly Major Maintenance Program. The Board of Port Commissioners awarded a $1.45 million construction contract to Griffith Company in April.